So, the fix was to build some retaining walls, back fill, and then throw a slab. Plus, LuckyL now has a car, and we have a "Venter" trailer, and the bike trailer (Parked here by a mate who does not have space for it), and 2 x XR200 Honda off-road bikes..
So, I mark out the proposed walling, and the foundations dig starts.
One by Zimbabwean laborer (with work permit) doing the digging. |
As is usual with these kind of jobs, you add on, make changes as you go along. So I had them dig an extra foundation for a low (1 - 3 brick high) wall. After pouring a slab on that, we would have a place to park the 2 x Honda's, and park the wheelbarrows, out of site, safe, and clean.
Then pouring the foundations. Amazing how much cement this consumes. I will list the total materials list later.
So the main wall has an average height of only 1.2m, but as it was to be a retaining wall, I wanted it 3 bricks wide. So, foundations are 600x 250. The smaller one, rhs of this above pic is for a 2 brick wall, so its 400x150 foundation.
We also had to accommodate a ramp, so that a) the bikes could be taken up and down, and the lawnmower needs to get to the lawn, and then back up to the lockup.
So a foundation for a wall that will form the side of the ramp. |
So, the retaining walls were done, and back fill started. The project was looking more and more like I had planned.
Aerial view of the planned lower slab, for the bikes and wheel barrows and stuff. |
The finished product:-
Bike trailer parking |
Ramp and bottom slab |
Another view |
Overview of the finished area! |
Ball on the wall |
Trailer, hooked up and secure, oh, and it tucks nicely behind the wall too! |
This is much simpler, narrow and shallow foundations for a 2 - 4 brick high single brick walls. Except for the corner unit, where I want to put a 5000lt Jo-Jo to catch up rainwater. There we going to pour a 100mm slab. For the rest, depending on how much building material I have left, 50 mm slab, or no slab. In that case I'm going to have some good soil delivered, and create vegetable gardens! Watch this space!!
2 Of the smaller "boxes" in front. The bigger "corner unit" for the Jo-JO is seen top right of the pic. |
So what did I have to buy?
1000 stock bricks. Do you know they now cost ZAR1.00 each (delivered)?
4m3 of concrete mix (That's stone and sand mixed)
2m3 of plaster sand
2m3 of building sand
64 bags cement
4m3 of unsifted building sand for filling (compacts very very well).
Needless to say the calculations were wrong. But after phase II of the project I have finished the bricks, including about 800 I had here left over for the original house build.
We have finished the building sand. The plaster sand that's left, maybe 2 wheelbarrows full will be used to finish the back fill of the corner unit. And there is just about enough building mix for the 2 proposed slabs. Oh, and now only 5 bags of cement.
Cost:-
Labour for phase I - ZAR 9,500
Materials total - ZAr 10,000
Labour phase II - ZAR 1,000 to date. Probaly another ZAR 600 or so to go.
After this, I don't think we will be doing any building work here for a while.
Salagatle!
3 comments:
Nothing is cheap nowadays is it?! Nice jobby tho' & I must say it looks very neat & tidy :-) Good idea about the towbar on/in the wall!
Looks great, bro. I would be complaining about the labour cost, especially in phase 1. Did those Zimbo's have Masters Degrees that you had to pay them that much? :-)
Thanx Jayne.
DMDad - so here's the thing, I got a few quotes, and this was by far the cheapest. Having said that, I now have the number for the guys that do the actual work, so can cut out the "front man", and thereby save a moer of a lot of money!
But, till you have the direct line to the worker, you kind of dependent on the broker.
So now it's R200 / day per worker, irrelevant of his position (Digger / mixer / builder / plasterer......)
That said, have you had a quote for building work lately? I think you will be surprised by the cost of the labor component. In fact, builders today say that the material is 50% of the cost, so I did ok.
Salagatle!
Post a Comment